๐Ÿงฎ TradeCalcsPRO

Excavation & Backfill Volume Calculator

Calculate bank, loose, and compacted cubic yards for excavation and backfill takeoffs. Model soil swell on haul-off, shrink on compaction, and deduct structural voids for foundations, pipe, and utilities.

Excavation Dimensions

ft
ft
ft
cu ft
%
%

Live Results

Raw Excavation (BCY)

29.63

Loose Haul-Off Volume (LCY)

37.04

Soil trucked off-site

Compacted Backfill Needed (CCY)

29.63

Space to fill after structural void

Loose Backfill Material Needed (LCY)

34.86

Material to order/haul in

How to Use This Calculator

  1. Enter excavation dimensions. Measure length, width, and depth of the cut area in feet.
  2. Set swell and shrink factors. Use default soil factors or adjust based on soil type โ€” clay swells more than granular soils.
  3. Deduct structural voids. Subtract foundation, utility, and footings volume that will not be backfilled with excavated material.
  4. Review BCY, LCY, and CCY outputs. Use bank cubic yards for cut volume, loose cubic yards for haul-off trucks, and compacted cubic yards for fill orders.

Formula & Example

Earthwork volumes are measured in three soil states. Each state reflects how the material behaves during excavation, hauling, and placement โ€” and the conversion between them depends on swell and shrink factors specific to your soil type.

  • Bank (BCY โ€” bank cubic yards) โ€” in-situ soil as it exists in the ground before disturbance. Excavation takeoffs start here: length ร— width ร— depth, divided by 27.
  • Loose (LCY โ€” loose cubic yards) โ€” excavated soil after it is dug and loosened. Volume increases due to swell (bulking). Haul-off trucks and stockpiles are measured in loose yards: BCY ร— (1 + Swell% รท 100).
  • Compacted (CCY โ€” compacted cubic yards) โ€” placed and mechanically compacted fill in its final in-place density. Backfill space after deducting structural voids is measured in compacted yards. Loose material to order accounts for shrink: CCY รท (1 โˆ’ Shrink% รท 100).

Excavation Volume (cu ft) = Length (ft) ร— Width (ft) ร— Depth (ft)

Excavation Volume (BCY) = Excavation Volume (cu ft) รท 27

Loose Haul-Off Volume (LCY) = BCY ร— (1 + Swell% รท 100)

Net Compacted Backfill Required (CCY) = Max(0, Excavation Volume (cu ft) โˆ’ Structural Void) รท 27

Loose Backfill Material Needed (LCY) = CCY รท (1 โˆ’ Shrink% รท 100)

Mechanical Compaction Practices

Compacted backfill must be placed in controlled lifts and compacted to a target density โ€” typically 90โ€“95% of Standard Proctor maximum dry density for structural backfill around foundations and utilities.

Lift thickness: Place backfill in lifts no thicker than 4โ€“8 inches loose before compaction. Thick lifts prevent adequate densification at the bottom of the lift and are a common cause of settlement.

Compaction equipment: Use a plate compactor or hand tamper for narrow utility trenches and tight areas around footings. Vibratory rollers or sheepsfoot rollers suit larger open excavations. Match equipment energy to lift thickness and soil type.

Moisture-density (Proctor test): Compaction efficiency peaks at optimum moisture content. Too dry and particles will not knit; too wet and pore water carries load instead of soil grains. A Standard Proctor test defines the moisture-density curve for your borrow material โ€” field moisture should be within a few percent of optimum before compaction.

Structural void interaction: Foundations, footings, pipe, and utility structures occupy volume within the excavation that will not be backfilled with native soil. Enter that combined volume as Structural Void โ€” the calculator subtracts it from gross excavation before computing CCY and loose backfill LCY. Haul-off volume is based on total excavation regardless of void, since all disturbed soil must still be removed.

Worked Example

A 30ร—20ร—6 ft excavation = 3,600 cu ft รท 27 = 133 BCY. With 30% swell: 133 ร— 1.30 = 173 LCY for haul-off. Backfill at 10% shrink: 133 รท 1.10 = 121 CCY needed.

Frequently Asked Questions

What over-dig tolerance should I allow around footings and utilities?โ–พ
Standard practice allows 6โ€“12 inches of working room beyond footing or pipe faces for placement, compaction equipment access, and bedding material. For deep footings, add the full over-dig width ร— length ร— depth to your excavation dimensions, then enter the footing concrete volume as Structural Void so backfill CCY reflects only the annular space around the structure. Utility trenches typically over-dig 4โ€“6 inches per side for bedding and haunch compaction.
How do swell and shrink percentages vary by soil type?โ–พ
Sand and gravel swell modestly โ€” typically 10โ€“20% โ€” and compact readily with low shrink (5โ€“10%). Clay and silt swell more aggressively (25โ€“40%) due to structure breakdown and can shrink 10โ€“20% when recompacted, especially if moisture is not controlled. Rock and blasted material can swell 40โ€“60% or more depending on fragmentation, with variable compaction behavior. Always verify factors with a geotechnical report or local DOT tables for your borrow source rather than relying on defaults alone.
When should I order extra material for compaction loss?โ–พ
The Loose Backfill Material Needed (LCY) output already accounts for shrink during compaction. Order an additional 5โ€“10% contingency on top of that figure for spreading loss, uneven subgrade, and field moisture adjustment. If you are importing select fill (not reusing native spoil), confirm the supplier's swell/shrink factors โ€” imported sand may behave differently from excavated site clay. For critical structural backfill, a proctor-verified shrink factor from lab testing is worth the cost on larger projects.
What is the difference between BCY, LCY, and CCY?โ–พ
BCY (bank cubic yards) is in-situ soil volume before excavation. LCY (loose cubic yards) accounts for swell when soil is dug and expanded โ€” used for haul-off truck sizing. CCY (compacted cubic yards) is volume after compaction for fill and backfill orders.
What swell factor should I use for clay soil?โ–พ
Clay and silty soils typically swell 25โ€“40% when excavated (swell factor 1.25โ€“1.40). Granular soils swell 10โ€“25%. Always confirm with a geotechnical report on commercial projects.

Related Tools

Explore more free calculators. Back to home

ADVERTISEMENT ZONE // CONTAINER_LEADERBOARD728 x 90