Excavation & Backfill Volume Calculator
Calculate bank, loose, and compacted cubic yards for excavation and backfill takeoffs. Model soil swell on haul-off, shrink on compaction, and deduct structural voids for foundations, pipe, and utilities.
Excavation Dimensions
Live Results
Raw Excavation (BCY)
29.63
Loose Haul-Off Volume (LCY)
37.04
Soil trucked off-site
Compacted Backfill Needed (CCY)
29.63
Space to fill after structural void
Loose Backfill Material Needed (LCY)
34.86
Material to order/haul in
How to Use This Calculator
- Enter excavation dimensions. Measure length, width, and depth of the cut area in feet.
- Set swell and shrink factors. Use default soil factors or adjust based on soil type โ clay swells more than granular soils.
- Deduct structural voids. Subtract foundation, utility, and footings volume that will not be backfilled with excavated material.
- Review BCY, LCY, and CCY outputs. Use bank cubic yards for cut volume, loose cubic yards for haul-off trucks, and compacted cubic yards for fill orders.
Formula & Example
Earthwork volumes are measured in three soil states. Each state reflects how the material behaves during excavation, hauling, and placement โ and the conversion between them depends on swell and shrink factors specific to your soil type.
- Bank (BCY โ bank cubic yards) โ in-situ soil as it exists in the ground before disturbance. Excavation takeoffs start here: length ร width ร depth, divided by 27.
- Loose (LCY โ loose cubic yards) โ excavated soil after it is dug and loosened. Volume increases due to swell (bulking). Haul-off trucks and stockpiles are measured in loose yards: BCY ร (1 + Swell% รท 100).
- Compacted (CCY โ compacted cubic yards) โ placed and mechanically compacted fill in its final in-place density. Backfill space after deducting structural voids is measured in compacted yards. Loose material to order accounts for shrink: CCY รท (1 โ Shrink% รท 100).
Excavation Volume (cu ft) = Length (ft) ร Width (ft) ร Depth (ft)
Excavation Volume (BCY) = Excavation Volume (cu ft) รท 27
Loose Haul-Off Volume (LCY) = BCY ร (1 + Swell% รท 100)
Net Compacted Backfill Required (CCY) = Max(0, Excavation Volume (cu ft) โ Structural Void) รท 27
Loose Backfill Material Needed (LCY) = CCY รท (1 โ Shrink% รท 100)
Mechanical Compaction Practices
Compacted backfill must be placed in controlled lifts and compacted to a target density โ typically 90โ95% of Standard Proctor maximum dry density for structural backfill around foundations and utilities.
Lift thickness: Place backfill in lifts no thicker than 4โ8 inches loose before compaction. Thick lifts prevent adequate densification at the bottom of the lift and are a common cause of settlement.
Compaction equipment: Use a plate compactor or hand tamper for narrow utility trenches and tight areas around footings. Vibratory rollers or sheepsfoot rollers suit larger open excavations. Match equipment energy to lift thickness and soil type.
Moisture-density (Proctor test): Compaction efficiency peaks at optimum moisture content. Too dry and particles will not knit; too wet and pore water carries load instead of soil grains. A Standard Proctor test defines the moisture-density curve for your borrow material โ field moisture should be within a few percent of optimum before compaction.
Structural void interaction: Foundations, footings, pipe, and utility structures occupy volume within the excavation that will not be backfilled with native soil. Enter that combined volume as Structural Void โ the calculator subtracts it from gross excavation before computing CCY and loose backfill LCY. Haul-off volume is based on total excavation regardless of void, since all disturbed soil must still be removed.
Worked Example
A 30ร20ร6 ft excavation = 3,600 cu ft รท 27 = 133 BCY. With 30% swell: 133 ร 1.30 = 173 LCY for haul-off. Backfill at 10% shrink: 133 รท 1.10 = 121 CCY needed.
Frequently Asked Questions
What over-dig tolerance should I allow around footings and utilities?โพ
How do swell and shrink percentages vary by soil type?โพ
When should I order extra material for compaction loss?โพ
What is the difference between BCY, LCY, and CCY?โพ
What swell factor should I use for clay soil?โพ
Related Tools
- Concrete Volume Calculator
- Asphalt Driveway Cost Estimator
- Fence Post & Material Calculator
- Concrete Block & Mortar Calculator
- Rebar Quantity Calculator
Explore more free calculators. Back to home